ASAP methdology

Former Member
0 Kudos

Hi Friends,

i am frequently i am facing this question.

which stage you entered in ASAP methodology? what you done in that stage?

Please explain me all stages and SD consultant work in that stages?

Advance thanks

Gopal

raoyaradesi@rediffmail.com

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hello Gopal,

<b>Please go through the following links given below............you will have a clear idea on ASAP methodology -</b>

<a href="http://www.sapfans.com/sapfans/asap/be_01_e.htm">Introduction</a>

<a href="http://www.sapfans.com/sapfans/asap/be_02_e.htm">Accelerated SAP</a>

<a href="http://www.sapfans.com/sapfans/asap/be_03_e.htm">Phase 1 - Project Preparation</a>

<a href="http://www.sapfans.com/sapfans/asap/be_04_e.htm">Phase 2 - Business Blueprint</a>

<a href="http://www.sapfans.com/sapfans/asap/be_05_e.htm">Phase 3 - Realization</a>

<a href="http://www.sapfans.com/sapfans/asap/be_06_e.htm">Phase 4 - Final Preparation</a>

<a href="http://www.sapfans.com/sapfans/asap/be_07_e.htm">Phase 5 - Go Live & Support</a>

<b>Reward points if helps</b>

Regards

Sai

Answers (6)

Answers (6)

Former Member
0 Kudos

Dear Gopal,

Go through the following threads:

Reward if it helps.

Regards,

Naveen.

Former Member
0 Kudos

Hi As per the replies u got hope u got a clear picture of ASAP methodology .

based on that u need to answer. E.G. If u r in project preparation u need to be with the decision making team .

In BBP u r suggesting some cut over strategy for the client .

In realization u r into core customization part doing the configuration part.

In Final prepn.

u r into trouble shooting aspects

finally u r into end user training and preparing end user doc . in go live and support.

Hope it will help u out .

Former Member
0 Kudos

Hi,

Gopal

ASAP Methodology consists of 5 Stages

1.Project Preperation

2.Business Blueprint

3.Realization(Customization & Configuration).

4.Final Preperation

5.Go live & Support.

Basing on your involvment you can describe the stage.

Regards,

Sridhar Reddy.P

Former Member
0 Kudos

Five Phases of ASAP methodlogy.

Phase 1: Project Preparation - The purpose of this phase is to provide initial planning and preparation for your SAP project.

Phase 2: Business Blueprint - The purpose of this phase is to achieve a common understanding of how the company intends to run its business within the SAP System. The result is the Business Blueprint, a detailed documentation of the results gathered during requirements workshops. The Business Blueprint document represents the business process requirements of the company. It is the agreed statement of how the company intends to run its business within the SAP System.

Phase 3: Realization - The purpose of this phase is to implement all the business process requirements based on the Business Blueprint. The system configuration methodology is provided in two work packages: Baseline (major scope); and Final configuration (remaining scope).

Phase 4: Final Preparation - The purpose of this phase is to complete the final preparation (including testing, end user training, system management and cutover activities) to finalize your readiness to go live. The Final Preparation phase also serves to resolve all critical open issues. On successful completion of this phase, you are ready to run your business in your live SAP System.

Phase 5: Go Live & Support - The purpose of this phase is to move from a project-oriented, pre-production environment to live production operation.

Additionally:

Some additional Infomation on ASAP methodology:

Phase 1 - Project Preparation

Change Charter - Goals and objectives of Organizational Change&#61550; Management

Project Plan - This is a first cut focusing on milestones and&#61550; Work Packages; details to come.

Scope - Sets the initial definition of the&#61550; project; input from sales cycle.

Project Team Organization - Sets the who&#61550; of the project: Standards & Procedures - Sets the why and how of the project.

Phase 2 - Business Blueprint - Requirements reviewed for each SAP Reference Structure item and defined using CI Templates (in the Q&Adb). Business Blueprint - This is the output of the Q&Adb and is the key document for Phase 3.

Phase 3 - Realization - Master Lists - Define business scenarios and R/3 transactions to be realized in the system. BPP - Business Process Procedures representing R/3 transactions; used for unit testing & documentation. Planning - Defines how the configuration will be done and how it will be tested. Development Programs - Provides details of the external programming requirements. EU Training Material - End User training material and process documentation.

Phase 4 - Final Preparation Stress & Volume Tests - Plans for confirming the production hardware’s capabilities

Cutover Plan - The details of how to move to the production environment and go live

Conduct End User Training - Delivery of the necessary levels of R/3 End User training prior to going live

Phase 5 - Go Live & Support: Ensuring system performance through SAP monitoring and feedback.

Reward points if helpful.

Regards,

Rajesh Banka

Former Member
0 Kudos

Hi Gopala Rao,

Pl go thr below links on ASAP Methodology:

ASAP METHODOLOGY:

http://help.sap.com/saphelp_47x200/helpdata/en/48/623972d55a11d2bbf700105a5e5b3c/frameset.htm

http://www.sapfans.com/sapfans/asap/be_01_e.htm

http://help.sap.com/printdocu/core/print46b/en/data/en/pdf/SVASAP.pdf

.

ASAP Roadmap (SAP Help)

http://help.sap.com/saphelp_47x200/helpdata/en/48/623972d55a11d2bbf700105a5e5b3c/content.htm

ASAP Methodology & ASAP Roadmap (SAP Service Marketplace) - Requires OSS Login

http://service.sap.com/asap & http://service.sap.com/roadmaps

Overview of the ASAP methodology - Richard W. Vawter, University of Southern California

http://www-rcf.usc.edu/~anthonyb/itp320/ASAP.ppt sd-fi integration

Reward if it helps