cproject - acountin error!!!

Former Member
0 Kudos

Hi All Gurus,

we are workin on cProject 4.

i have made all settings in spro of cprojects @ accounting, but in evaluation tab, i m nt able to c the values..

what cud be the error ?

<b>i have defined cost/revenue rates</b> and also selected "<b>use rates from cprojects</b>" still not visible in evaluation.

however i can c the rates in resource >> costing tab.

waitin with points

Niranjan

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Follow this link

<u>http://help.sap.com/saphelp_cpro31/helpdata/en/home.htm</u>

Regards

Rehman

Reward If Useful

Answers (4)

Answers (4)

Former Member
0 Kudos

Hi Rehman,

received your File

i have done all settigns

but still unable to c cost in evaluation

do i have to create internal order even if im using rates defined in Cprojects.

Thanks

Former Member
0 Kudos

Hi,

Yes you have to create Internal Order,

Rgds

RK

Former Member
0 Kudos

Hi,

Follow this link

<u>http://help.sap.com/saphelp_cpro31/helpdata/en/home.htm</u>

Regards

Rehman

Reward If Useful

Former Member
0 Kudos

Rehman,

I dont want to use the rates from R/3. i Would be using rates defined in cProjects confid only...

still the evaluation tab looks blank...

so is it that after creating an internal order, i ll be able to c costing data in evaluation tab...

Points given ...

thank

Former Member
0 Kudos

<b>helppppppppp</b>