ATP

Types of Availability Check in Sales and Distribution

Processing

There are three types of availability check:

_ Check on the basis of the ATP quantities

_ Check against product allocation

_ Check against planning

The following SD-specific control features need to be maintained in Customizing:

_ Checking group

The checking group controls whether the system is to create individual or collective

requirements in sales and shipping processing. In addition, a material block for the

availability check with transfer of requirements can be set here. The checking group can

also be used to deactivate the availability check. This option was created especially for

the assembly order so that when the bill of material is exploded in the assembly order,

the individual components, if necessary, can be classified as non-critical parts as far as

procurement is concerned.

The checking group specifies in combination with the checking rule the scope of the

availability check. It is proposed in the material master record on the basis of the material

type and the plant, and copied into the sales and distribution documents.

_ Checking Rule

You use the checking rule to control the scope of the availability check for each

transaction in sales and distribution. You also specify whether the check should be

carried out including or excluding replenishment lead time. The individual checking rules

define by transaction, which stock and inward and outward movement of goods should

be taken into account for the availability check.

_ Schedule line category

You can control with the schedule line category whether an availability check and

transfer of requirements should be carried out in the sales documents. The possible

settings for this at schedule line level are dependent on the settings in the requirements

class which is determined from the requirements type of the material.

_ Delivery item category

The delivery item category can be used to control whether an availability check takes

place in deliveries.

Requirements type

The various requirements are identified by their requirements type. The requirements

type refers to the requirements class and its control features.

_ Requirements Class

The requirements class contains all control features for planning such as relevance for

planning, requirements planning strategy and requirements consumption strategy. In

addition, it is specified at a global level whether an availability check is to take place for

the material in the sales and distribution documents on the basis of the ATP quantity

(ATP = available to promise) and whether requirements are to be passed on. A finer

degree of control can be obtained for sales documents using the schedule line category.

Replenishment lead time is only included in the check performed on the basis of the

ATP quantity.

Prerequisites

An availability check can only be carried out if the following prerequisites have been fulfilled:

_ The control elements described above for the availability check must be maintained in

Customizing for Sales and the relevant assignments made to the sales transactions

_ The availability check must be switched on at requirements class level and - for the

availability check in the sales documents - at schedule line category level

A requirements type must exist by which the requirements class can be found

_ A plant must be defined. It can either be proposed from the customer or material master

record or can be entered manually in the document.

_ A checking group must be defined in the material master record on the Sales/plant data

screen in the Availability check field

Configuring entries of the Availability Check

IMGSDBasic fncsAvailability check and TORAvailability checkAvailability check with ATP logic or against planningDefine checking groups

You can use SAP std checking groups of 01 for summarized reqts or 02 for daily reqts or u can create ur own.

The columns total sales and total deliveries are selection options whereby u can configure a checking rule to sum up reqts to post to MRP either individually or by day or week.

Column 5, Block qty; set this block if u want several users to be able to process the material simultaneously in different transactions without blocking each other. The No Check indicator is used when u want a material to not be relevant for an ATP check.

Defining a material block for other users. The Block checkbox is an indicator that enables u to block the particular material from being checked for availability if it is already being checked at the same time by another user.

Defining the default value for checking groups. However should no entry exist for the checking group in the material master record, one can set a default value per material type and plant.

Controlling the availability check. In this section, u tell the system what stock on hand and what inward and outward movements of stock it must take into account when performing the availability check. These settings are based on the checking group that is assigned to the material master record and the checking rule that is predefined and assigned to the sd transaction. The carry out control for the availability check must be maintained for both the sales order and delivery.

TOR

IMG  SD  Basic fncs  Availability check and TOR  TOR

A line item in the sales order creates a schedule line. The schedule lines in the sales order transfer the requirements through to MRP. You can select the docs on which you want the TOR to happen. For ex, not for quotations.

The TOR aims to ensure the ordered materials are available for the requested delivery date. The TOR can be set for individual or for collective requirements (materials mastersales/plant view).

The TOR is dependent on the following data:

The reqts type, reqts class, checking group and schedule line category.

The reqts type and class are determined in the strategy group (material masterMRP3)

For TOR to be carried out, a few criteria need to be met:

Plant assigned to line item level, schedule line category should be switched on at TOR, TOR must be switched on at the reqts class level, checking group must be defined and allocated to the material master record (sales/plant view in the availability check field)

The reqts class is the controlling factor for the availability check and the TOR for all sd types.

Configuring the TOR:

1) Use std 041 reqts class or copy and rename it. Use the indicators to select if this reqts class must carry out an availability check and/or a TOR.

2) Define the reqts types. A reqts type is allocated to a single reqts class and not vice versa. It is based on the item category and the MRP type of the material.

3) Assign the rqts type to the relevant item category in the sales order and the MRP type found on the material master record.

You can select an alternative search strategy where u assign the reqts type to item category and MRP type. Can select source as 0, 1 or 2. (1 = Item type and MRP type strategy).

4) The TOR and Availability check can be selected/de-selected at the schedule line category level.

5) Block qty confirmation in delivery blocks. This is used to block the reservation of the TOR from MRP.

6) Maintain requirements for TOR. Requirements can be used to determine that the TOR to MRP is not carried out unless a number of conditions are met.

Availability Overview = CO09  order qty, sd doc no, item no, requirements class.

Stock requirements list = MD04  sd no or dly no, line item, schedule line placing the demand

Stock overview = MMBE  total stock per company, then plant followed by storage location, and finally a breakdown per batch.

Regards,

Rajesh Banka

reward points if helpful.

Answers (6)

Answers (6)

Former Member
0 Kudos

Dear Shivaji,

Availability check (ATP check) is used to check whether a product can be confirmed in a sales order, based on the fact that enough stock is available or can be produced or purchased on time. The product is reserved in the required quantity, and ATP requirements are transferred to production or purchasing.

You can also carry out availability check in simulation. This is called availability information.

Visit the following links for information regarding availability check:

http://help.sap.com/saphelp_crm40/helpdata/en/b6/de3efc6bbcdc4b948d466857a10323/content.htm

http://www.sap-img.com/sd028.htm

Reward points if this is helpful.

Regards,

Naveen.

Former Member
0 Kudos

Availability check can be configured both at requiremnt class and at the schedule line categories level.

Whilst the availabilty check at the requirement class level via global and mandatory configuration the schedule line catgry availability check deals with the order.

It is mandatory that the reqmnt class is flagged off for avlblty check and the schdelu line cat need not be.

The following are the mandatory for Availability check to happen--

1. Must be swithced on at the requirment class level and at the schedule line level.

2. Reqmnt type must exist by which a requiremnt class can be found

3. There must exist a plant and is defined

4.Checking group must be defined in Material Master records(it controls whthr the system is to create individual or collective reqmnt)

A combination of checking gropup and checking rule will determine the scope of availbaility check.

Following are the configuration parameters:

1. <b>Define Checking Groups</b>

Menu Path: SPRO>SD>Basic Functions>Availability Check and Transfer of Requirements> Availability Check with ATP Logic or Against Planning>Define Checking Groups

You define checking groups with which you specify the type of requirements records the system is to create when processing sales orders or deliveries

2. <b>Define Material Block for Other Users</b>

Menu Path: SPRO>SD>Basic Functions>Availability Check and Transfer of Requirements> Availability Check with ATP Logic or Against Planning>Define Material Block for Other Users.

3 .<b>Define Checking Groups Default Value</b>

Menu Path: SPRO>SD>Basic Functions>Availability Check and Transfer of Requirements> Availability Check with ATP Logic or Against Planning>Define Checking Groups Default Value.

4. <b>Carry out Control for Availability Check</b>

Menu Path: SPRO>SD>Basic Functions>Availability Check and Transfer of Requirements> Availability Check with ATP Logic or Against Planning>Carry Out Control for Availability Check.

5. <b>Define Procedure by Requirements Class</b>

Menu Path: SPRO>SD>Basic Functions>Availability Check and Transfer of Requirements> Availability Check with ATP Logic or Against Planning>Define Procedure by Requirements Class.

6. <b>Define Procedure for Each Schedule Line Category</b>

Menu Path: SPRO>SD>Basic Functions>Availability Check and Transfer of Requirements> Availability Check with ATP Logic or Against Planning>Define Procedure for Each Schedule Line Category.

7. <b>Determine Procedure for Each Delivery Item Category</b>

Menu Path: SPRO>SD>Basic Functions>Availability Check and Transfer of Requirements> Availability Check with ATP Logic or Against Planning>Determine Procedure for Each Delivery Item Category.

8. <b>Checking Rule for Updating Backorders</b>

Menu Path: SPRO>SD>Basic Functions>Availability Check and Transfer of Requirements> Availability Check with ATP Logic or Against Planning>Checking Rule for Updating Backorders.

9. <b>Define Default Settings</b>

Menu Path: SPRO>SD>Basic Functions>Availability Check and Transfer of Requirements> Availability Check with ATP Logic or Against Planning>Define Default Settings.

Former Member
0 Kudos

hi shivaji,

AVAILABILITY CHECK:

Availability Check is an integral part of the business process. It determines if the desired delivery quantity can be met on the desired date. The availability check takes into account the respective activities that must be carried out before a delivery can take place. This includes the scheduling for picking or packing times & the time taken to produce or obtain the material as well as many other background functions

SPRO- IMG- SD- Basic Functions- Availability Check & TOR- Availability Check- Availability Check with ATP Logic or Against Planning.

Backorder Processing: is the processing of a backorder, which in itself is a sales order that has not been confirmed in full or not confirmed at a certain delivery date.

Rescheduling: is a proposal of how confirmed quantities already assigned to sales orders can be reassigned to other orders that have a higher priority, such as an earlier delivery date.

ATP: stands for Available to Promise. It is the process of checking the available quantities of a material. The ATP quantity is equal to warehouse stock plus the planned receipts (incoming stocks). ATP takes in to account all movements into and out of the warehouse. If selected, it can check the stock examined for ATP that can be safety stock, stock in transfer, stock in quality inspection, & blocked stock, although the planned receipts & planned issues of the stock associated with ATP may be purchase orders, purchase requisition, planned orders, prodn orders, reservations, dependent reservations, dependent requirements, sales requirements & delivery requirements.

Replenishment Lead Time: (RLT): is the time needed to produce the requested stock. It can be the time taken by the business to produce a material or the time taken to externally procure the mat from vendor. This includes goods receipting time. RLT is only used when doing an ATP check. The value of the RLT for a material is specified on the MMR record.

• The RLT for an externally procured material. This is determined based on the total of the processing time for purchasing, the planned delivery time & the goods receipt processing time. These setting can be made on the Purchasing & MRP 2 view of the MMR.

• The RLT for an internally procured material. This is based on the in house prodn time, found in the MRP 2 view, & the goods receipt processing time or alternatively on the total replenishment lead time, which is found in the MMR on the MRP 3 view.

• If a sales order is created, there is no available stock, and the ATP check is set to include RLT, the system will automatically confirm the desired quantity for the end of the RLT based on whether the material is externally or internally procured. It will still give a confirmed date according to the end of the lead-time. Should there be partial stock available, the system will confirm this partial stock available, the system will confirm this partial qty and move the remaining qty to the end of RLT. Thus it does not do an availability check outside RLT. If the RLT is three days for a specific material, it will not do an availability check outside of those three days, as it automatically thinks that it will definitely have the stock on the fourth day.

Hope it helps. Pl reward if useful.

Thanks

Sadhu Kishore

Former Member
0 Kudos

&#61557; Available to Promise (ATP) performs stock availability checks on schedule lines to confirm delivery dates of ordered materials.

&#61557; The ATP quantity is calculated from the warehouse stock, the planned inward movements of stock (production orders, purchase orders, planned orders), and the planned outward movements of stock (sales orders, deliveries, reservations).

Availability checking verifies - before you even complete the order entry - that you have sufficient quantities on hand to satisfy a new order. If you do not have enough on hand to ship right away, SAP determines in real time when the desired quantity will become available.

&#61557; ATP takes these elements into consideration when confirming inventory to order:

&#61550; requested delivery date

&#61550; requested quantity

&#61550; warehouse movements

Former Member