Project System(PS) - Milestone Settings.

prabu_kaliappan
Participant
0 Kudos

Hi Friends,

Pls. Send me the Usage of Milestone in Project progress and Milestone trend analysis.

What are all the config. has to do?

Looking for your speedy response.

Regards

Prabu K

Accepted Solutions (0)

Answers (1)

Answers (1)

madhan_narlapuram
Contributor
0 Kudos

Milestone billing is typically used for billing projects, such as plant engineering and

construction projects. Such projects often include a series of milestones that mark the

completion of different stages of the work. In the SAP R/3 System, milestones are defined

in a network along with planned and actual dates for the completion of work. The milestones are also assigned to the billing dates in the billing plan.

IMG configuration requires :-

1. Maintain billing plan types for milestone billing in OVBO.

2. Define date description in SM30 - V_TVTB.

3. Maintain Date Category for Billing Plan Type IN OVBJ.

4. Allocate date category in SM30 - V_TFPLA_TY.

5. Maintain date proposal for Billing Plan Type in OVBM.

6. Assign Billing Plan Type to Sales Documents Type in OVBP.

7. Assign Billing Plan Type to Item Categories in OVBR.

8. Define rules for determining the date in OVBS.

reward if useful