i have two doubts in the TP/VS scenario of SCM 5.0

1. when creating multi stage planning for the shipment, the system gives a error complaining "that the order cannot be delivered"

2. the vehicle combination (MTr) we created where is it used in the system,

Thanking you in anticipation.

regards,

Sandeep

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi Sandeep,

There are various reasons for message 'Order can not be delivered' Following are the possibilities

1) No lane maintained between source & destination location or the lane is not valid

2) The order weight or volume exceeds the vehicle capacity (split required)

3) Incompatibility is maintained in the system

4) Order can not be scheduled in the planning horizon (if the duration is more than the planning horizon)

5) No vehicle resources maintained in the optimizer profile or if the resource is not extended to Live Cache

Multi-modal hierarchy is required only if you are planning a multi-modal shipment & not multi-stage shipment.

If you have created MTr combination, then it is used in typical scenario os trucks & trailer. You will have to maintain active & passive vehicles in the system & then you can use them using MTr combination.

Hope this satisfies your queries. In case if you have further doubts, you refer back the question.

Thanks & Regards

Sandeep Patil

Former Member
0 Kudos

Do you have the multi-modal hierarchy created? This needs to be created and assigned in the SPRO in order to do this.

Former Member
0 Kudos

Hi Sandeep,

Point 1. Could you please give the error message number you are getting?

Point 2. IF you are talking about Means of Transport - MTr ?

The means of transport connects your vehicle resources to the transportation lanes in TP/VS.