on 05-15-2007 3:59 AM
hi,dear all:
When I set wbs to "clsd",can system check the purchment order's gi/ir balance of the wbs?(the account assignment of the po is the wbs)
If it can not ,is there any else method can do this?
thank you!
Hi Jian Mao,
Yes, when you change the WBS elemnt to "CLS" status, system will wheck any Open PR's, PO's and Final confirmation of the Activity assigned to that.
For closing the PR's or PO's set deletion flag on header or item level OR set the delivery completed flag in PO.
For Activities you need to confirm them manually using batch or one-by-one.
Hope this will answer all your requirement.
Reward me accordingly.
Harisha