Hi everyone

What would a SAP SD Consultant do on a normal working day ? let us say he is in realization phase of project.

Thanks

Sara J

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

hi,

just to add...

A functional consultant evaluates the demands in talking with the customer's representatives, transforms the essence into an abstract and algorithmic business model. Hence, he identifies the use cases and transforms them into logical and technical views.

Then the main task starts: customizing the respective business area and making sure the system reacts in the manner according to the constraints of the requested use case.

The consultant documents the settings and prepares proper guidelines that allow other consultants to do further changes or repairs with due efforts.

The consultant takes care that proper training is given to the users and that the system is usable, performing appropriately and the business flow is complete and correct.

During go live he assists the technical staff by testing the behaviour of the system.

After go live he guarantees that the procedures remain usable and consistent in real live situation and proposes enhancements.

The main duty of a consultant is to transfer external know-how to the client. It is not manpower that counts but intelligence, understanding of processes, a feeling for defects and general a common sense.

Role of a Functional Consultant in an End To End Implementation

When you talk about the role of a Functional consultant in an end to end implementation, I think it won't be possible for me or anybody to define everything but I will try to summarize it:

1. Functional consultant is expected to generate knowledge about the current business process, design current business flows, study current business processes and its complication, in all we can say getting through with current business setup. Flow diagrams and DFD are prepared, most of the time in Vision format, all this forms the part of AS IS document.

2. Everything configured has to be documented as per their categories in the form of predefined templates, these have to be then approved by the team leads or who ever the consultant is reporting to.

3. Mapping and GAP analysis is done for each module, I have seen people defining integration after mapping, gap analysis and configuration is done, but as per my experience in implementation, it is a simultaneous process.

4. Before starting configuring future business processes in SAP, the DFD/ERD are prepared, this documentation is called TO BE, which can be also siad as the result of mapping and gap analysis.

5. Sometimes Functional consultants are also expected to prepare test scripts for testing the configured scenarios.

6. End user manual and user training is also expected from F.Consultants.

The project normally starts off with a Kick off meeting in which the team size, team members, reporting system, responsibilities, duties, methodlogy, dates and schedules, working hours which have been predicided are formally defined.

ASAP, it won't be possible for me to explain it here, but all I can tell you about it is that it is SAP standard implementation methodology, which SAP prescribes but is not mandatory for any company to follow, such as IBM follow some blue Methodlogy, some companies follow typical SDLC steps, ASAP stands for Accerlated SAP, you can find all the steps on SAP site, through google, reading it from there won't give you a great knowledge about ASAP but will obviously get you to know the definitions of various term.

hope it helps.

Thanks

Sadhu Kishore

Answers (4)

Answers (4)

Former Member
0 Kudos

Hi Sara J,

In realization Phase, The day of SD consultant goes with:

1. Checking the Objcts developed by ABAPers

2. Provide Test data

3. Do Unit Testing

4. Intergration testing

5. Modifying the Unit Test /Integration Test Scripts (if required as required by business)

6.Preperation of Production Test Scripts

7. Modifying & Checking the Developed Objects - so that they are as per FS and check data picking logic for each fields

8. final preperation & checking the FS for Data Migration etc

9. training of Core-Team.

9. Preparing of User Manual. ETC

are some of the regular works in a SD consultant's day.

Reward if it helps

Regards

Srini

Former Member
0 Kudos

HI,

The purpose of Phase 3 is to configure the R/3 System, in order to have an integrated and documented solution which fulfills your business process requirements.

In this phase, configuration of your system is carried out in two steps: Baseline and Final Configuration. The Baseline configuration is designed to configure about 80% of your daily business transactions and all of your master data, and organizational structure. The remaining configuration is done in process-oriented cycles. The Business Blueprint is used as the guide for the system configuration, done using the Implementation Guide, which will be described in detail in this chapter. After this, data transfer programs, as well as interfaces, need to be tested.

Main work packages of Phase 3

1)Business Process Master List (BPML)

2)Baseline configuration and testing

3)Uploading the BPML Scope to R/3

4)Generating a Business Process Master List

5)Customizing R/3 with the Implementation Guide

6)Configuring the Implementation Guide

Please reward points if it is helpful.

Regards

Sasikanth.Ch

Former Member
0 Kudos

During the <b>Realization Phase in ASAP implementation</b>, following are the activities are carried out:( Just adding some more info to Rajesh mail)

I elaborated some points below for your understanding.

1. <b>Base line Configuration</b>- Here we will be doing module wise configurations and integration.

2. <b>Unit Testing</b> – Documenting so tthat required configurations are working fine.

3. Modification in Configuration, as per requirement.

4. Preparation of Function Specs for Development

5. Integration Testing.

6. Testing of Developments.

7. <b>Preparation of Templates for Master data upload</b>: Data management group will be using these templates to upload Master Data using LSMW/ BDCs etc.

8. Training Core-Team for Process mapped.

9. Preparing User Manual.

& so on ............................

Br,

Sarma PBS

Former Member
0 Kudos

In the Realization Phase, following are the activities the consultant will be occupied with:

1. Configuration

2. Unit Testing

3. Modification in Configuration, as per requirement.

4. Preparation of Function Specs for Development

5. Integration Testing.

6. Testing of Developments.

7. Preparation of Templates for Master data upload.

8. Training Core-Team for Process mapped.

9. Preparing User Manual.

& so on ............................

Regards,

Rajesh Banka

Reward points if helpful.