We are trying to use APO for Shop Floor Planning.
I want to know, can SAP - APO (Optimizer Run) give shiftwise planning instead of day bucket ? i.e. instead of daily requirement, 3 shifts requirement saperately ?
Thanks in advance.
Rajan
Hi Rajan,
SNP is bucketed planning and the most granular bucket is a DAY.
So in SNP you cannot do shiftwise planning. You need to use PPDS for shiftwise planning.
Thanks,
Somnath