Revenue is not calculated in cProjects

Former Member
0 Kudos

Hi,

I am using cprojects with Task Based accounting Integration with Multi Level controlling using WBS. When I do a transfer cost is calculated but not the revenue. Can anybody let me know why this happens.

I have set

1.Costing is possible in Cprojects and

2.Revenue Calcualtion in Cprojects (not sales pricing)

Best Regards,

Joseph.

jose_sandy@yahoo.co.in

Accepted Solutions (1)

Accepted Solutions (1)

schneidertho
Advisor
Advisor
0 Kudos

hi joseph,

have you maintained an amount in the respective cost/revenue rate plus assigned a revenue cost element to the rate in ERP?

cheers

thorsten

Former Member
0 Kudos

Yes I have maintained the Revenue Cost Element and the Revenue in the ERP.

Best Regards,

Joseph.

jose_sandy@yahoo.co.in

Answers (1)

Answers (1)

schneidertho
Advisor
Advisor
0 Kudos

Hi Joseph,

to be honest in that case I am also quite clueless.I have only used the revenue calculation together with role based calculation. But I would expect it to work the same for the task based scenario.

Last idea I have: when you look at the WBS elements created (or are you using an ad-hoc cost estimate?) - are they marked as revenue elements?

Best regards