on 05-09-2007 11:31 PM
Dear Gurus
I want to know how we can link SAP Plant Maintenance(PM) & Microsoft Project (MSP). There is something like OPEN PS which can do this integration.
Client wants that Maintenace order with all opeartion can be downloaded to MSP & he can do scheduling there which will be helpful for him for Shut down purpose.
I request & appreciate the earlier response....
Regards
Ashok
Hi,
you can externally schedule your orders.
1. In customizing set for which orders you need external scheduling.
2. Use these functional modules to fulfill whatever functionality is required. PM_ORDER_EXTERN_SCHED_APPOINT
PM_ORDER_EXTERN_BOOK_DEFAULT
PM_ORDER_EXTERN_SCHED_DIALOG
PM_ORDER_EXTERN_SCHED_DEFAULT
READ_WORKLOAD
Read more documentation about these function modules to know the details about them.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.