Costing in cProjects 4.0 - Material costs not reflecting

Former Member
0 Kudos

Hi,

In cProjects 4.0, i have replicated the cProject to PS project. I wish to capture the material costs in the project. How should i proceed ?

Please suggest.

Regards,

Amit

9820502246

amitssawant@gmail.com

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member189058
Active Contributor
0 Kudos

Hi Amit,

cProjects has not field to caputure material costs.

You may however, create an additional field and use that to capture material costs in cProjects. You will need to map this additonal field to the material cost field in PS while replicating project from cProjects to PS. I am not sure of how you will do this. See if there is any BAdI that can help you.

Regards,

Reema.

<i>pl award all useful points.

Do post back if you find a solution.</i>

Message was edited by:

Reema Shahbazkar