During MRP Run system is generating PR but the PR date is not same as MRP Run date

Former Member
0 Kudos

Hi All,

Thanks in Advance.


Current Scenario :


MRP Tpye : PD


Procurement Type : F (External Procurement)


During MRP Run system is generating PR but the PR date is same as Sales Orders date.


Requirement:


System should generate PR but the PR date and MRP Run date should be same. It should create PR for Sales Order on MRP Run date not on Sales Order date.


For Example :


Sales Order Date is 10th of Oct but MRP is running on 4th of Oct, so system should generate PR for given sales order on 4th of Oct.


Kindly provide the solution for the same. Your help will be highly appreciated.


Regards

AV

Accepted Solutions (0)

Answers (1)

Answers (1)

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello AV

What you are observing on your system is according to the standard design of MRP type PD. With this MRP type, system will always try to match the requirement and the replenishment proposal date.

Try to use an MRP type such as VB or V1 and check the results.


Regards,

Caetano

Former Member
0 Kudos

Hi Caeteno,

Thanks dear but already client is using VB and it is working also. But they want the same PR generation system in PD also.

So is there any exit or enhancement you can suggest so I can work it out. Its really important. 

Regards

AV

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi Anish

It makes no sense to use MRP type PD on this scenario.

You could try to use BAdI MD_CHANGE_MRP_DATA to manipulate the requirement dates or another BAdI to change the requisitions date, but it would be a frankenstein solution and I would not recommend it at all.

If you really want to bring your purchase requisitions earlier, it would make more sense to use a safety time, but you cannot guarantee that the requisition date would be the MRP date.

Regards,

Caetano