Hello Gurus,
Can you please provide me detailed pros and cons of using MRP Area.
Things we should keep in mind before implementing St. Loc MRP Area.
Many thanks.
Amit Kumar
Hello Amit,
The MRP area represents an organizational unit for which material requirements planning is carried out independently .
it can be a group of materials in the plant or storage location or Sub contracting vendors
please refer the below threads for better understanding
MRP Area - Special Planning Processes - SAP Library
MRP AREA CONFIG & PROCESS | SCN
Regards,
Venkatesh..
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Kindly go through below document for understand MRP Area.
When you have defined MRP areas for storage locations , you have assigned the materials, the plant MRP area is reduced by exactly storage locations. This is because they are now to be planned separately.
As soon as you have activated materials requirements planning with MRP areas, this type of MRP is active at client level, that is, MRP will be carried out in this way in all plants.
Material requirements planning with MRP areas cannot be reversed.
If you have any other doubt kindly revert back.
Thanks & Regards
Sandeep Kumar Praharaj
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.