Message Payload after Processing in PO

Former Member
0 Kudos

Hi All,

We have SAP PO 7.5 system sending data to ECC.

When PO receives message it performs some transformations then sends message to ECC.

We can see received message payload in message log of message monitor in pimon but we want to see payload which PO is going to send to ECC after processing.

Can you suggest how can we check this in PO.

Thanks,

Shivam

Accepted Solutions (0)

Answers (2)

Answers (2)

vicky20691
Active Contributor
0 Kudos

Ryan has given you the correct answer. Just to help you with screenshot.

Regards,

Vikas

Ryan-Crosby
Active Contributor
0 Kudos

Hi Shivam,

By default the system only logs the message version before the mapping step (MS).  If you want to see the message persisted after transformation then you can enable it within the specific flow properties, or if you want it to be globally then you need to adjust one specific server property so it will log the AM step.  You have the choice to add the AM step or you can make it so the system would only log the AM step and stop logging the MS step.  One extra note is that you can always figure out what the AM step result would be by executing your mapping steps within the test frame of the ESR.

Regards,

Ryan Crosby