Hi SAP expert,

I wanna ask about one time formula of bill of material.

Can I create one time Bill of Material in SAP PP?

If I can , How can I make it?

Please help and suggestion

Thanks and regards

Anita A

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member194456
Contributor
0 Kudos

Hello

Could you please elaborate your requirement on one time BOM

Regards

SS

anitaarifin04
Participant
0 Kudos

Dear Mr.Saurabh,

I need to create bill of material which only use for one time only.It's similar with one time customer in sales order.I need one time bill of material for rework process.

former_member208398
Active Contributor
0 Kudos

Anita,

You can directly add components at order level, if required. Creation of order without BOM/Routing is possible. Search in the forum.

BR,

Rajen

0 Kudos

Hi,

     You can use CS61 that is Sales order BOM.

Regards,

Amit

former_member194456
Contributor
0 Kudos

Hello

AS per my understanding, there is no one time BOM concept.

If you think that the BOM should not use further after the Production, you may put the BOM components manually in the Production order

OR

You may create the BOM and change its status to Not active. This may also lead to stop further usage of BOM.

Also if the rework order is created with CO07 than it is suggested to add component in production order level

Hope this helps

Regards

SS

0 Kudos

Hi,

     For Rework process create a seperate BOM usage & assign it with selection ID & BOM application.

     Then assign that BOM application in order type dependent paraments.

Regards,