How to set lead time in work center?

former_member232086
Participant
0 Kudos

Hi All,

We are producing different categories of items…for some items which are producing in specific work center and for those items we need 3 days as processing time.

Is there any filed in work center/routing /PO to update lead time/processing time same as GR processing time in MRP 2?

Pls advise

Accepted Solutions (1)

Accepted Solutions (1)

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

I suggest you to take a look on the following documents, which explain how to create a work center or routing:

Regards,
Caetano

former_member232086
Participant
0 Kudos

Dear Caetano,

thanks for the useful documents, we are creating routing on daily basis but dont know how to put lead time which should not affect any scheduling process..this lead time should work same as in case of GR processing time in MRP tabs

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

Did you already try to use a teardown formula? You may have to create your own formula and add an extra activity on your standard values.

Regards,

Caetano