Did you mean: 

PPM to MS Project export duration is zero

Former Member
0 Kudos

Hi ,

When we export PPM Project to MS Project then in MS Project file duration column contains value zero as well as Finish Date is same as that of start date for all the tasks.

Any one please suggest how to fix this.

Regards,

Manzoor Khan

Accepted Solutions (0)

Answers (1)

Answers (1)

judith_gabriel
Contributor
0 Kudos

Dear Manzoor,

have you mapped the fields in customizing under
"SAP Portfolio and Project Management -> Common Functions -> Import and Export of Project Data -> Microsoft Project Integration > Assign Fields for Export from Project Management"

for Base System Object: PDMP

Sub Object: MT

Best regards,

Judith

0 Kudos

Dear Judith,

Thanks for the reply.

Yes, there is a mapping in customization in above said SPRO path. Please find attached document.

Regards,

Manzoor Khan

judith_gabriel
Contributor
0 Kudos

Dear Manzoor,

I cannot see the field-mapping of "Duration" in your screenshot.

best regards,