My customer getting forecast unplanned requirements value in MD04 screen as 81 nos for a material .

Customer is using MRP type : P1 :Now he wants to know how forecast vale value calculated.

Thank you in advance

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member185450
Active Contributor
0 Kudos

Hello Venkat,

Please check whether that material is maintained the forecasting view in the material master??

if the forecasting view is maintained with forecasting values the same will get updated in the MD04

please check and let us know, share your MD04 Screen shot if possible

Regards,

Venkatesh..

venkat_v
Participant
0 Kudos

Hello

Thank you for your reply.

As requested MD04 screen provided below '

regards,

Venkat

former_member185450
Active Contributor
0 Kudos

Hello Venkat,

These unplanned requirements has been arrived from MM02--> Forecasting View--> Forecasting values

so please delete those values through MM02 or through Program: RMCPMLOE

Another solution is in OMDQ against MRP Type MRP Ind. Forecast: as Not to be included in planning

system will not plan your forecasting requirements

Regards,

Venkatesh..