on 09-24-2016 1:46 PM
Dear All,
I have configured scoring model for NPV and ROI for both manual and calculated fields. Scoring Model is linked to Probability Technical Success field.
But while clicking on Score information, the system is only considering on NPV but not other 3 field values. I confirm that the scoring model service is mapped to RIH object (see below).
Thanks for any suggestions.
Regards,
AP
Any further help ?
Regards,
AP
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello
Can you confirm the ranges you maintained for each of these under scoring model attributes?
Take note that depending on the data type of the field you need to maintain the relevant range - e.g. if the data field for NPV is defined as type CURR in table /rpm/item_d then you need maintain the range "Ranges - Currency" in this setting. Or if NUMC then you maintain "Ranges - Numeric" or if CHAR then you maintain "Ranges - Text". Please check all
Also ensure your ranges includes a value associated with 0 so that a score can be calculated if the user doesn't maintain a value
Regards
C
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello C,
Thanks for our reply, yes I know about the data type of the field in RPM table and Ranges (Currency, Char, Text) should match in scoring model.
The value ranges are given in the above screenshot. However I found that NPV_PLAN, ROI_PLAN and ROI these fields are not present in /RPM/ITEM_D table . Did I miss anything ?
This is the reason the system is giving 0 value in scoring model.
Ex : For your reference I have put one screenshot of scoring attributes of NPV_PLAN.
Regards,
AP