Progress Analysis in CNE1 is not giving any values for POC

Former Member
0 Kudos

Hello SAP Gurus,

I am not able to view Progress Analysis- POC  in SAP PS in T Code CNE1 for POC.

Please note the business flow as follows-

We have investment Projects configured in the system.

We have created Network(Header account assigned) & activities for the same.

Please note that, no costs are captured on Networks.

Actuals for the project will be captured through MIRO as we are having non valuated goods receipt.

My requirement is to track the physical progress of Projects through Confirmation of Activities.

Progress Analysis configuration & execution steps

I am using WORK(0000000006) - Degree of processing from confirmation method , Standard "100" progress version to calculate the POC.

I have maintained the following below entries for Progress Analysis in the activity. Below attached is the screen shot of the same.

Now i have confirmed the activities with some degree of processing in CN25. 

Now i am running CNE1, with the selected Progress version, Period & Year.

Inside the transaction of CNE1 , i am not getting any POC values. 

Please let me know ,  if i missed any step or some configuration.

Require your help & suggestions to help me out with the POC values.


Regards,

SS

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member198686
Active Participant
0 Kudos

Hi shalanki,

Please check below two links fyr,

Progress Analysis Process - Project Progress - SAP Library

Regards,

KRK

Former Member
0 Kudos

Hello Ravi,

My query remains unanswered. Let me put it this way-

I want to calculate POC for Prorjcts, based on the confirmation of the activities. Please note that the Activities created do not carry the actuals. They are having the quantum of work to be executed for completion of the Project.For your information, I have not created any Statistical Cost Elements for calculating the POC. Please suggest the best possible way out to calculate the POC for the Project.

Regards,