on 09-22-2016 7:57 AM
Hi
I am after customization in Solution manager 7.1 SP12 for two requirements :
Incidents should be closed if change request completed.
Incidents should only confirmed if successor documents completed.
Till now what I did and that is not working is :
In SPRO -> sap solution manager -> capabilities -> change control management -> change request management framework -> Make settings for change transaction type.
I have configured successor and predecessor Transaction with user status and assigned actions but not sure why it's not working.
Regards
Prakash
Hi,
I assume that you are creating the CR from the incident.
In that case you need to maintain the predecessor document setting as YMIN with corresponding values.
Regards
Abhishek
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Abhishek
Yes, I am using CR followup from incidents.
What I want achieve is, if a followup documents created from incident then it should not confirmed until followup document completed.
If change request completed then request for change and incident should be confirmed automatically.
Regards
Prakash
Thanks Abhishek,
Now it's resolved, there was some configuration issue.
Regards
Prakash
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
94 | |
11 | |
10 | |
9 | |
9 | |
7 | |
6 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.