Greetings Experts,
I am trying to use the Date Scheduling and Project Planning Board functionality for the first time. Our user has a clear requirement as under :-
Major Activities performed - (% weightage)
1.Engineering - 10
2.Procurement - 30
3.Execution - 40
4.Capitalization - 20
Each major activity has multiple sub-activities(activity elements/milestones) which should have individual weightages allocated.e.g.
1.Engineering - 10%
a.ABC - 30%
b.XYZ - 70%
Based on date scheduling for each sub-activity, once completed, system should calculate % completion of major activity say e.g.
1.Engineering - 10% - Completion % - 50
a.ABC - 30% - Completed - 100%
b.XYZ - 70%
Where can % weightages be allocated?
How can Scheduled Start/Finish dates be allocated to sub-activities, instead of getting auto picked w.r.t main activities
Please suggest.
regards
Dear Asif/ken,
Thank you for reverting, was finding it difficult to proceed even at basic level. But since my last post I've gained understanding of scheduling and project Analysis report. First let me share what I've done in the system based on what the user requires.
1. Gave % weight-age to specific wbs based on work. In this case WBS Engineering holds 15% value.
2. Gave % weight-age and assigned dates to specific activities which would sum upto 100%.
3. Then executed CNE5 and got the output to somewhat where I want to be.
Now my question is -
1.How do I get the WORK overall % to be 100 instead of 400 and calculate as the activities get confirmed?
2.How to make the WEIGHT % calculate automatically as the activities get confirmed.
Please guide.
Thanx in advance.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Mazal,
You need to maintain POC % Weight, Progress Version & POC Calculation Method in Activity Progress Tab as mentioned below in screen. First you need to do configuration for all this in SPRO.
Yes, when you confirmed Activity POC weightage % will automatically calculated in the System.
First you need to Run Transaction CNE1 then you can see the result in CNE5 Report.
Please follow the same steps as mentioned in these threads.
http://scn.sap.com/thread/1127555
http://scn.sap.com/thread/3234944
Regards,
ASIF
Dear Asif,
Thank you for your revert.
As you can see the user has pre-defined -:
1. % of 4 major activities - Engineering - 15, Procurement - 35%, Execution - 40%, Capitalization - 10%.
2. Sub-activities under each major head have been given individual weightages which calculate to 100% , so in other words if :-
e.g. for Engineering if all activities are
1.Act 1 = 25% --> Confirmed = 100%
2.Act 2 = 30% --> Confirmed = 100%
3.Act 3 = 15% --> Confirmed = 100%
4.Act 4 = 30% --> Confirmed = 100%
then Engineering should be 15% else show % based on number of sub-activities completed of 15%.
My question is before I go ahead ans do the customization in SPRO, will the stated steps by you achieve this?
Please guide.
regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.