on 09-21-2016 8:11 AM
Hi Everyone.
I am maintaining Milestone Trend Analysis Scenario.
But facing some issues:-
1. I have maintained project and assigned 2 milestone on 2 wbs element with 50 % projec complettion
2. Release the project
3. open the cn41n and created the project version and saved
4. open the milestone trend analysis t.code CNMT
getting the error :- No Milestone have been selected
Please anyone guide where I am missing it.
Thanks
Rahul
Hi Rahul,
Milestone trend analysis is a simple method for analyzing the dates in a project and comparing them with planned data. You use it to recognize trends and deviations from the planned schedule quickly .
The scheduled dates of the milestones, which are relevant for the course of the project, are compared at various points in time. Deviations from the planned schedule are made apparent. In the graphical form a MTA chart is used, which is triangular where the sides are the times axes. The milestone dates are plotted against the report dates.
Please understand the purpose and usage of Milestone Trend Analysis as explained in this link.
Milestone Trend Analysis (MTA) - Project Progress - SAP Library
Regards,
M. Asif
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.