Investment Management - Copy Version Assignment IMA6

former_member299514
Participant
0 Kudos

Hi All

While doing copy version IMA6 from one fiscal year version to another as shown below:

we are facing an error

I am trying to copy cost planning version in IM from year 2016 ver 0 to year 2017 ver 1

Year 2017 Ver 1 has been set up.

I have kept the same exchange rate type P in both the versions but still the error message is displayed.

Have any ideas to remove the error?

Regards

Suman Misra

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member299514
Participant
0 Kudos

Any inputs on this?

asifkamal
Explorer
0 Kudos

Hi,

Go to Transaction OKEQ and change the Exchange Rate Type for Version each Fiscal Year as required. I think Both Version have to be same Exchange Rate Type. Maybe this will help.

.

Please reward points if this is correct

Regards,

M. Asif