on 09-16-2016 5:34 AM
Does any one know how to enable CProjects so you can choose to schedule either top down or bottom up perhaps where there is a pop up selection that allows you to change scheduling method (top down / bottom up) for each individual project
Many thanks
Trish
Hi Trish,
there is an option introduced with Customer Connection Cycle 3 for PPM to influence the type of scheduling for each project - independent of your project type customizing.
Have a look to this note https://launchpad.support.sap.com/#/notes/2183391
It is not down-ported to PPM 4.0-6.0, it is only for PPM 6.1.
It introduces a switch 0012/0005 in customizing
It is not a pop-up that appears inside your project but a radio-button to selection either to schedule top-down or bottom up.
br,
Peter
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Peter
Much appreciated
Trish
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
11 | |
6 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.