Hi,

In SMI scenario with replenishment order, is there any way we can match PO number range from ECC system while creating RO in SNC.

I am finding it difficult to match the current number range in ECC with SNC PO (created by RO).

Thanks,

Vaibhav

Tags:
Former Member
Former Member replied

Hi Vaibhav,

There is no standard way of checking the current PO number range in ECC, while creating a RO in SNC.

Normally we create a separate number range for SMI PO and then create same number range in SNC. This will automatically make sure that both POs number are in sync in ECC & SNC.

Dont use this number range for any other scenario, this will again create same problem of inconsistency.

Regards,

Rahul