Confirmation of tasks under Subprojects

Former Member
0 Kudos

Hi All,

I have created a cProject. Assigned a subproject to one of its tasks. Now I wanted to confirm the tasks under the subproject. But the Confirmation field is greyed out. Its a non input field. So I can't enter the time on the confirmation field. Same problem is happening with the Master Project Task to which I have assigned the subproject.

Pls tell me how to confirm the tasks for subprojects ?

Warm regards

Purnendu

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Check the confirmation parameter opst or opk4

Also check control key opj8