on 09-15-2016 6:17 AM
Hi Friends,
We are planning to migrate from SAP PI 7.1 dual stack to PO 7.5 single stack. We have many third party systems where PI is sending/receiving requests. We are thinking to infirm all out third party vendors about this upgrade. What are all the action items from them after the upgrade?
We are using adapters like File, Idoc, Soap, advantco, XI, etc..
Thanks,
Ramakrishna
guys any inputs ???
I heard PI end-points will be changed. what are all the additional changes required by third party vendors?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Ram,
Br,
Manoj
User | Count |
---|---|
87 | |
10 | |
10 | |
10 | |
7 | |
6 | |
6 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.