on 09-14-2016 7:34 AM
Hello Friends,
My Scenario is I have made changes in Project Profile which is already in use on Production. now User wants all new changes should be apply to current running projects too.........
Is there way to apply new changes done in Project Profile to Existing Project???
Regards,
Omkar Deshpande
Hi,
Chnages done in the project profile will reflect in new projects created after transporting the changes only.
Retrospective changes cannot be done to the existing projects.
Regards
Ritesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thank you guys for help
creating the program to make changes as per new requirement
Closing This Thread
Regards,
Omkar Deshpande
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Omkar,
It purely depends on what changes you are trying to make in the project profile.
If the fields in the WBS element or Project already greyed out, then there is no way to change the data as it is locked, so these fields will be reflected with new project as per the advice given by others.
Regards
Terence
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Agree with Ritesh..Retrospective changes are not done..
If you want to change old projects.. Need to do it manually or write a program to change the settings..
still you may not be able to change a lot of things..
regards
Sammar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.