Hi Experts,

We are on ECC 6.0 EHP7 service package 7. I have created Project structure with Netwrok activity, but when I am trying to schedule Project through Project planning board. System is not showing project structure with WBS and Network structure.

Kindly please help and suggest.

Please check below screen shot.

Regards,

Arvind T.

Accepted Solutions (0)

Answers (2)

Answers (2)

MTerence
Active Contributor
0 Kudos

Hi Arvind,

When you click on the description column, does it shows the description ?

Recently we have lot of posts similar to this, may be check for SAP Notes or raise to SAP.

Regards

Terence

sammar81
Employee
Employee
0 Kudos

Hi Arvind,

It is an issue with the SAP GUI. Check the patch level of your SAP GUI

Regards

Sammar

Former Member
0 Kudos

Hi Sammar,

Thanks for your reply.

Are you talking about SAP Log on pad?

We are using SAP GUI version - 7400.1.0.1093

May I know which patch required?

sammar81
Employee
Employee
0 Kudos

yes Correct.. I think it is corrected in SAP GUI 740. 3.0, Raise an OSS to get the lastest one..