Statistical WBS in Purchase otder

Former Member
0 Kudos

hi

is it possible to use Statistical WBS as account assignment for material procurement PO with item category Q?

it is not allowing in our system, I am cross checking if it is due to some customisation issue or standard does not allow for it. We need it to hit Project stock account for which material has separate valuation class.

stiram

Accepted Solutions (0)

Answers (4)

Answers (4)

former_member230675
Active Contributor
0 Kudos

Hi,

Statistical WBS can not carry real cost hence it wont allow.

Statistical WBS you can use it for Budget control as an auxillary account assignment along with another real CO object.

Thanks

Abdul

former_member198686
Active Participant
0 Kudos

Hi Sriram,

Pls check below scn links may be help full to you,

how to creat commitment for PO PR but not creat... | SCN

https://scn.sap.com/thread/999593

Regards,

KRK

Former Member
0 Kudos

Hi,

I do not think you can use statistical WBS in PO.

Usage of Statistical WBS in material PO does not add any value to the process. You need a real cost object to book the cost. You need a cost center which can be assigned with the statistical WBS.

sammar81
Employee
Employee
0 Kudos

Hi Sriram.

Is the statistical WBS having Cost Center where finally the cost should hit?? As just statistical WBS will not allow account assignment to PO..

Regards

Sammar