Dear Friends,
We have requirement to integrate SAP with Oracle Primavera.
1) I have installed Enterprise project connector in our ECC system
I am very new to this kindly help me on the below points
1) What are the list of basis activity involved for this integration.
2) To establish connection DBCO is enough or any other procedure is there.
3) If possible kindly share basis activity document for the SAP and Oracle Primavera Integration.
Regards,
P.Marudhu Pandy.
Hi Marudhu,
Please refer below SAP note which has give all detail steps and requirement for Primavera integration.
2297855 - SAP EPC Primavera P6 EPPM Integration: setup/settings/troubleshooting
Regards,
Anil Bhandary
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
There is no requirement of PI for EPC integration, you need a java stack on which you have deployed the EPC related patched. So once you deploy the patch you will find the CTC template in EP which you have to run and provide all necessary input of Source i.e. ECC and Target of Oracle Primevera.
Activity has to be done by Basis consultant only and not PI.
Above I have mentioned High level steps. For detail steps kindly refer the note which was shared earlier which has all details.
Regards,
Anil Bhandary
User | Count |
---|---|
87 | |
10 | |
10 | |
10 | |
7 | |
6 | |
6 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.