Hi,
We currently have an issue where the SM_CCL: OBJECTS for Custom Code Management is causing the following entries in SM21:
X MESSAGE BRAIN 299: CL_RSR_VAR_RUNTIME CONSTRUCTOR-01-
Based on note 2323195, this happens when the limit of active handles is reached and that this is an unrecoverable error.
I was wondering if I can do something with the job or anything in CCLM to run in chunks so as not to open a huge number of handles.
Regards,
Jing
Quick update ... as advised by SAP, I implemented all the CCM related notes mentioned in RTCCTOOL. I re-ran one of the SM_CCL: OBJECTS job ... The runtime went down from 4.5 hours to 30 minutes. Anyways, I did not get the SM21 messages when I ran the job
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Jiing,
check this note as well..
Gagandeep Singh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
78 | |
10 | |
9 | |
7 | |
6 | |
6 | |
5 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.