on 09-02-2016 8:22 PM
Dear Seniors,
Please advise on the best practices of this challenge.
We are using SAP ERP -> MES landscape for manufacturing. There are operations which have rework required.
If we use an additional operation in SAP for rework
- we plan let's say 10% but the actual quantity reworked can be different, from order to order.
- we get capacity requirements which are not consumed until the order is finished, if the reworked qty. is not exactly 10%
If we use the rework loop in ME
- the rework is done in the same operation, we would not need another additional operation
- but there is no capacity planned in SAP for this
Many thanks for your suggestions,
Alex
Hi,
Rework orders were planned for implementation in the upcoming release of ME 15.1. I doubt it is available in ME 15.1.1.x.
After the release you will be able to find the information in the online help.
Regards,
Sergiy
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.