A production order with BOM component quantity value of 3 decimal points reserves in WM (LS24) with a rounding value of only 2 decimals.
Example:
Production order = 144 mm
LS24 = 0.150 m
Is there somewhere to set inorder to reserve the same quantity in LS24?
Thanks in advance
Hello Suresh,
Yeah it is possible.
In LS24 report click on Base Unit of Measure filed and select the preferred UoM.
Please note that preferred UoM is maintained for that material.
BR,
Olet