thanks for your reply but client wants in see the value in PO also so what to do?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
The field in yellow of your screen cannot be used since the account assignment category B or D close this field. And the interface TM -> always do it by this way (because it uses the service entry sheet).
So unfortunately this is not possible in the standard system.
You can check the price in "LIMIT" or "SERVICE" tabs of PO.
BR
Gian
Hi,
Planned service is when you fill the services manually in service tab of PO with values and the service entry sheet is according with this information. If you use the limit tab, the service entry sheet will be ticked as unplanned.
The integration between TM-MM uses the limit tab and thus unplanned services.
Regards.
Gian
Thanks for your reply now my problem solved.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
The purchase order created from a transport cost document does note use the EKPO line information. The price is store in service line information (Service or Limit tabs). Probably in PO History you will found the Service Entry Sheet created with the correct cost.
Regards.
Gian
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
11 | |
11 | |
6 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.