planned order start date on non working day

Former Member
0 Kudos

Hi All,

We are using PPDS for planning, and in the planned orders, start date is on a non working day.

On checking the factory calendar which is mapped to the resource are looking fine, where we mentioned 5 days working.

can you please provide your views on this. Thanks in advance.

Regards,

Yasar 

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi Brahmankar and Vinoth,

Thanks for your valuable comments, have changed the shift timing earlier it was till 24:00:00 and we have changed to 23:59:59 and it is fine now.

Thanks,

Yasar

Former Member
0 Kudos

Hi,

Check the time stream of Calendars maintained under each planning (Production Plant) location in Location Master, as well.

Just my thoughts

Regards

Vinoth

rupesh_brahmankar3
Active Contributor
0 Kudos

Hello,

Please check the heuristic Strategy Profile if Non- working time is active.

Refer SAP consulting note 397989 - PP/DS: Scheduling (Documentation)

Best Regards,

R.Brahmankar