Hello Gurus!!

If confirmed sales order is changed  to have a new shipping date. Is it possible for the availability check to run automatically for sales orders even when a date or quantity is updated after the sales order was originally created?


Thank you.


Ashish Arora



Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

This message was moderated.

0 Kudos

Hi Ashish,

1. you can do Availability check manually from Change Order Screen(VA02) or update sales order(V_V1) transaction.

2. To automate this, you can perform BDC on V_V1 and schedule a job on that.

For more details to automate data in Sales Order, you can study the FM 'BAPI_SALESORDER_CHANGE'

-Sunny

ashish_arora6
Participant
0 Kudos

HI Sunny,

Actually, I dont know in standard if we are changing(date or qunatity) any confirmed sales order, then system will run availvality check or not?

I have confusion in this.

Please help.

Regards,

Ashish Arora

0 Kudos

Hi Ashish,

Well answer to your question is NO. System wont run availability check automatically, you have to command the system to do it.

-Sunny

ashish_arora6
Participant
0 Kudos

Hi Sunny,

I checked in the system, availability check is automatically running when I am changing the confirmed quantity such that it will exceed the available stock.

Regards,

Ashish Arora

0 Kudos

Hi Ashish,

When i update the quantity or date, it is showing this popup.

and after that it shows availability control screen and i have to confirm the availability by clicking on that green button.

So how it can be automatic check if you are confirming by manual intervention?

-

ashish_arora6
Participant
0 Kudos

Hi Sunny,

Yes, it should show availability control screen.

Earlier, I thought it would not show and we need do it manually.

Regards,

Ashish Arora