on 08-29-2016 11:20 AM
Hello Experts,
is there a way to know utilization of resource for every product planned in the resource ?
i.e if there are two products A and B planned in resource R1, and total utilization is 80 %, is there a way to know how much is the utilization of product A
Regards
Alin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Alin
Yes it should be possible to see the similar information in PPDS in detail scheduling board.
In Detail scheduling board you can go to resource view and double click on capacity requirement row in specific bucket where capacity requirement > 0 then you will get another window where you can see all the planned order/Process orders for respective articles which are planned for respective resource.
I hope this information will help you. Please do let us know if you have any additional information.
Thanks and Regards
Amol