Dear Team,
I am doing Overall Budget for my Project WBS and availability control is set to Active during Overall Budget Release in configuration. Below are setting for same.
We had configured the tolerance limit as follows.
But, When I am Creating Budget in CJ30 and release the same CJ32, availability control is not triggering automatically as configure.
To activate same I need to manually run CJBN.
Can advise me on how to fix this issue?
regards
Atul Rajmane
hi,
1. ensure that you have the correct budget profile in the project
2. how do you release (cj32), do you input specific WBS element or the entire project? it should be the entire project so that AVAC can be activated properly.
3. also, check if you have a user status in the project which prevents the AVAC.
i agree that the AVAC should get activated when you use the CJ32 transaction.
regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Atul,
When you are checking overall Budget, remove the release check in the config
Regards
Terence
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Maria,
As per SAP, It should get activated after the release of an Overall budget in CJ32.
In our Local IDES same with the same setting, availability control gets activated at the time of Overall Budget Release. But, it is not working QA/PRD.
Any note or setting we not missing since with Reconstruction of availability control its get activated.
Kindly advise
Regards
Atul Rajmane