FMAVC005 Annual budget exceeded

Former Member
0 Kudos

Hi gurus

When I'm creating a purchase order, the next message appear:

FMAVC005

Annual budget exceeded by 1.000 CLP (FM PB Availability Control) for document item 00010

But for the budget center/commitment item combination I load budget, in the attached pictures you can see this.

Additional information: I'm usgin S4Hana 1511

Regards,

2 REPLIES 2

iklovski
Active Contributor
0 Kudos

Try initializing AVC via FMAVCREINIT. If it doesn't help, check FMAVCT table and make sure that that for the line in question the figures seem to be correct. Make sure, that budget types you are using are well defined in AVC settings as budget available for consumption.

Former Member
0 Kudos

Hi Eli

I rarn FMAVCREINIT and you can see the result in the attached picture:


In our table FMAVCT we have no records.

The AVC configuration is attached.