on 08-23-2016 1:06 PM
Hi All,
Can anyone tell me if I created group work centre of 5 people so when I'm going to assign multiple people on workcenter more 5 people, I can assigned and system wouldn't restrict me so kindly what is the reason behind that strategy and if it's SAP standard functionality, kindly so share with me help.sap link on which is mention that this is SAP standard.
Regards,
Faizan
Hello,
As per standard practice work center should be various for various person/group of person or machine/group of machine.
so in standard system workcenter won't be allow to pur multiple person responsible.
here you are refereeing multiple person would be involve in any task then why not planning in workforce planning a package of sap project system.
WFM enable you to planning for multiple person on one task.
Regards,
Sanjeev
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.