Ammount Assigned in CJ30 is not equal to total Line Items CJI3 + CJI5

Former Member
0 Kudos

Hi Experts,

My client controls Investment with PM Orders associated to WBS Element.

I have this problem:

1. In CJ30 there is an ammount Assigned of 14,879.38  USD

2. However, in no other report I can see this ammount.  I have reviewed CJI3 (Shows 14,633 USD), CJI5 (there aren't commitment line items), S_ALR_87013558 (Shows 14,633 USD and 10,975 PEN) and I can´t find the same ammount.

Budget control is with reference to Assigned ammount, but is very confused because this ammount doesn´t appears in other reports.

I have attached screenshots.  Please your help.

Regards,

Pepe Lucho

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Pepe,

In CJ30, can you please also check the entries by changing "Controlling area currency" to "Object currency".