Hello Gurus,
We are assigning one WorkCentre to multiple projects in project system. So we want to see the report.
what are standard tcodes available and tables from PS side.
Siddu
Hi Siddu,
You can use CN47N via dynamic selection enter the work centre, give either the project or wbs element or network (give a range or put *) and execute
Regards
Terence