on 05-02-2007 2:54 PM
Hello Everybody:
My Planning area is a copy of SNP94 also the data views, I was wondering what kind of SNP aggregates in pl. area are to be assigned to Keyfigure 9ACASUP in order to remove the conflict between the selection and keyfigure, and how do I assign.
Thank you
Sadat
9ACASUP should be assigned to the following standard aggregates:
9ALA
9ALORE
9AMALARE
9AMALORE
9AMARE
9ARE
9AREPR
As I say however, these are the standard aggregates, at which level are you selecting your data?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Visu:
I do have all required data in my model and version. I mean location, products, resources, PDS as production resource and Tlanes. My consistency check shows no errors.
I could run the SNP plan in data view SNP94 (1) with APO location-production, where as when I make selection for resource I dont see any selection in data view SNP94(2) i.e capacity check.
Please advice, thank you.
Sadat
Harish:
Your guess is right the resource has been assigned to the model using SCE, is there a way of checking the PDS in SCM box, I could only generate PDS in CFM1 selection for my product and locations, when I tried for the same combination for PPM I could generate nothing.
I wonder/ doubt as mentioned by Ayyagari the consistency of rounting in R/3 and I hardly have experience in checking that in R/3. What could be a the right way to check there consistency in R/3. I am not working with a whole lot but just few assemblies.
Thank you
Sadat
Before checking the routing information in R3, check it in APO PDS
Goto transaction : /SAPAPO/CURTO_SIMU - Display Production Data Structures
Input the product and location and look for the resource in the PDS.
Or use the WUF- where used list transaction .
Click on the details and then goto the ACTIVITIES tab and then click on details again. You should be able to see the resource number in the Modes tab.
************************************************************
Let me know If this helps
All this applies If your question is basically that in the capacity planning book, you are able to see the resource number in the selection id.
However you are not able to display the products processed under the resource.
Kindly explain in detail, If this is not your problem.
Ayyagari:
Thank you so much for your reply, I checked the PDS the activity do not show any resources in mode, When I check from the drop down the list do appear for the resources for the location I am planning.
I wonder what may be the problem, is that the routing incorrect here?
********************************************************************************************
I am not able to see any product/ resource/ location in selection ID.
Thanks again.
Sadat
Sadat,
Problem with the R3 Routing.
Goto transaction CA03 in R3 and input the material and location and display.
You should be seeing the work center assigned.
Also check whether in the production version, the wokcenter has been assigned to the material.
Use C223( You may not have access) to view.
Let me know If this helps
The production planners( Or Master Data Team) in your team must have access to C223, Ask them to maintain the routing information in the production version.
Activate the PDS integration model and check the PDS in APO, whether you are able to see the resource and
Then in your capacity planning book, you should be seeing all the products... Good Luck..
Hope this helps...
Hi,
9ACASUP is capacity. Are you asking about the calculation type for disaggregation. In our system, we just assigned "S"(Prorata).
what do you mean by "in order to remove the conflict between the selection and keyfigure"?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.