08-15-2016 11:32 AM
Hi Team,
Can someone suggest to avoid this error for mass FPMA run.
I have gone through the scn some helpful threads but nothing working.
Please suggest.
Reards,
Honey
08-15-2016 1:23 PM
Honey:
You need to maintain the number ranges for this mass activity. The error occurs because at least one of the ranges currently assigned has been fully exhausted. You will need to unassign the number range interval which is no longer usable, as well as possibly add new ones.
regards,
bill.
08-15-2016 1:23 PM
Honey:
You need to maintain the number ranges for this mass activity. The error occurs because at least one of the ranges currently assigned has been fully exhausted. You will need to unassign the number range interval which is no longer usable, as well as possibly add new ones.
regards,
bill.
08-16-2016 8:23 AM
Hi Williams,
Still i am facing same issue even though i maintained same.
Please suggest.
Regards,
Honey
08-16-2016 9:29 AM
Hi Honey,
You have to maintain multiple mass number ranges.
The maintenance of the mass number ranges is directly proportional to the number of jobs that you are using for executing the FPMA job.
If you are using 5 jobs in FPMA run, then you should have at-least 5 mass number ranges defined in customizing.
Hope it helps.
Thanks,
Amlan
08-16-2016 11:26 AM
Hi Amlan,
I am executing first time in dev system, and mapped the number ranges as provided.
It's single job for testing, even i tried for multiple number range assignment at mass process.
do we expect that any basic thing i am missing out.
Regards,
Honey
08-16-2016 3:07 PM
Hi Honey,
You need to maintain the number ranges for object, EMMA_RUNID
Go to SNRO and give the object as EMMA_RUNID and maintain the number ranges,
Then execute FPMA. I think it should be fine.
Thanks,
Amlan
08-17-2016 6:20 AM
08-17-2016 5:59 PM
This is outstanding....Thanks Amlan for great inputs.
It's working fine now.
Regards,
Honey
08-17-2016 5:59 PM