Budget Commitment at Shopping Cart in SM in PDP Scenario

Former Member
0 Kudos

Hi Experts,

We require FM budget commitment at the time of creation of shopping cart in SRM. We are on SRM 7.3 version with Classic Scenario.

Please help.

Regards

1 ACCEPTED SOLUTION

iklovski
Active Contributor
0 Kudos

Hi,

Please, consult notes:

https://launchpad.support.sap.com/#/notes/900825

https://launchpad.support.sap.com/#/notes/828231

Commitments are created at the back-end exclusively.

Regards,


Eli

View solution in original post

1 REPLY 1

iklovski
Active Contributor
0 Kudos

Hi,

Please, consult notes:

https://launchpad.support.sap.com/#/notes/900825

https://launchpad.support.sap.com/#/notes/828231

Commitments are created at the back-end exclusively.

Regards,


Eli