Planning element tick default at WBS

Former Member
0 Kudos

Hi All,

My requirement is to get default check of 'planning element' when I'm going to create WBS so for that purpose, I have created substitution and prerequisite and apply that substitution on project profile but after that, I'm still not getting planning element tick default. Below is screen shot of substitution.

Regards,

Faizan

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Faizan,

Your pre-requisite condition and substitution condition should not same otherwise it wont work.

Let's say you want to apply this substitution for project profile 'CP', then change the pre-requisite condition to PROJ-PROFL = 'CP' and keep the substitution as is.

Hope this helps.

Best regards

Aditya

Former Member
0 Kudos

Hi Aditya,

Issue was resolved as I was defining value 'X' in prerequisite and substitution as prerequisite should be input with '' value.

Regards,

Faizan