on 08-11-2016 2:25 PM
hello
I have WBS elements and assigned to them activities.
When I create new activity in the activity new settlement rule is created as well.
New settlement rule is created as FUL settlement rule type.
I need to create PER type of settlement rule. Where can I change it to create PER type in such situation?
Regards
Adam
Hello,
The settlement type of new network activities is decided by table TKB2C.
I guess there is no customizing transaction to change this table, but you could go to transaction SM31 and change the entry below for the default rule "PS1" in view V_TKB2_2 from GES to PER.
Nevertheless as "PS1" is a standard SAP entry, the preferred way would be to create a new default rule as copy of "PS1", change the parameters of your new default rule and assign it in customizing to your network type. New default rules are created in view V_TKB2_1 and the assignment customizings are very well explained in document .
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.