Hi Experts,
I have one particular question for the Work Order Integration, if I understand correctly, when the Preventive Maintenance Order is sent to SAP ME, the status of the ME Resource is going to be changed to "Schedule Down", is there a standard procedure to avoid this behavior?
I want to send the Preventive Work Order to SAP ME, but I do not want to change in automatic the status to Scheduled Down.
Thanks for any suggestion guys.
Hi,
You need to modify the Equipment Status Change Request XSLT in MII. The standard XSLT changes status to 4 - scheduled down. Change this to 1 - Productive for example
Thanks
Steve